    Commercial case study / DSV

    One regional IT team.
    Site-specific installation work.

    How InstallPros coordinated site-specific Starlink installation work with DSV’s regional IT team and local facility contacts.

    Transport & logistics United States · Canada · Puerto RicoCommercial Starlink installation

    The challenge

    Every building brings a different set of requirements.

    DSV’s regional IT team coordinated installation requests across facilities. The correspondence shows practical requirements: suitable mounting, cable routes, equipment-room access, landlord approvals, and local scheduling.

    InstallPros worked between that regional team, local facility contacts, and installers to move individual sites through survey, installation, and handoff.

    The work

    Coordinate centrally. Solve the site details locally.

    Site surveys

    Establish the mounting position, access requirements, and cable path before arranging the work.

    Building coordination

    Work with local contacts on roof access, landlord requirements, insurance documentation, and safe site entry.

    Mounting and cable routing

    Coordinate the installation around the building’s roof, available lifts, and route to the IT equipment area.

    IT handoff

    Connect local installation activity with the regional IT team and document where the equipment and incoming cable are located.

    Documented milestones

    What the project records establish.

    November 2024

    Puerto Rico

    Survey, cable planning, and installation

    The site survey identified a mounting location and cable route into the equipment room. The installer reported completion on November 14, followed by DSV’s acknowledgment on November 15.

    August 2025

    Innisfil, Ontario

    Commercial access and mounting coordination

    The work involved a non-penetrating roof mount, contractor safety requirements, and lift access. The installer reported the equipment set up on August 18, with account setup and data-room cable cleanup still noted.

    December 2025

    New Albany · USQWB003

    Installation confirmed by the customer

    InstallPros reported installation completed on December 22. DSV’s site general manager confirmed it was installed on December 23 and supplied images; IT requested additional handoff-location documentation the next day.

    These are individual documented milestones, not a claim that every requested location was completed. Installation confirmation does not establish measured uptime, automatic failover performance, or financial savings.